Project Status
UNWI 1 & 2 - Part of the Elkhorn and Natomas Boulevard Sewer Connection Project
| Fall/Winter 2007 | Construction Began |
| Status | The entire UNWI 1 & 2 alignment runs along the East Drainage Canal between the New Natomas Pump Station and Bridgecross Drive. As preliminary construction activities progress, activities will move north along the canal. Possible lane shifts and lane closures may be necessary where roads cross the alignment.
|
| Fall 2008 - Spring 2010 | Underground tunneling |
| Spring 2008 - Summer 2010 | Manhole construction |
| Winter 2010 | Construction expected to be complete |





The entire UNWI 1 & 2 alignment runs along the East Drainage Canal between the New Natomas Pump Station and Bridgecross Drive. As preliminary construction activities progress, activities will move north along the canal. Possible lane shifts and lane closures may be necessary where roads cross the alignment.