Project Status
UNWI 1 & 2 - Part of the Elkhorn and Natomas Boulevard Sewer Connection Project
| Fall/Winter 2007 | Construction Began |
| Current Work | ![]() UNWI 1 & 2 Tunnel Tunneling is progressing north from the New Natomas Pump Station next to the East Drainage Canal. |
| Spring 2008 - Summer 2010 | Manhole Construction |
| Winter 2008 - Spring 2010 | Underground tunneling |
| Winter 2010 | Construction anticipated to be complete |