Project Status
Upper NW Interceptor Sections 3 & 4 Part of the Elkhorn Boulevard/Natomas Boulevard Sewer Connection
What's Next?
The UNWI is divided into sections 1 through 4. Two construction projects are scheduled. One construction crew will construct sections 3 & 4 (this project) and the other will construct sections 1 & 2 (in North Natomas).
Project Schedule for UNWI Sections 3 & 4
| Fall 2006 | Complete final design phase |
| Spring 2007 | Construction Began |
| Early 2008 | Construction expected to complete |