Upper Northwest Interceptor Section 9 (UNWI 9) and Associated Northeast Area (NEA) Relief Projects Construction*

UNWI 9 Mid-2007 - Fall 2008
Northeast Area Relief Trunk Sewer 2 (NEA-2) Mid-2007 - Fall 2008
Northeast Area Relief Trunk Sewer 1 (NEA-1) Fall 2008 - Mid-2010

 

Construction hours are between 7 a.m. and 8 p.m., Monday through Friday, and between 8 a.m. and 8 p.m. on Saturday and Sunday. Certain exceptions will apply.

*This schedule is subject to change and is contingent upon weather, a successful bid process and other construction issues.