Agenda Item Staff Reports May 10, 2006
Support documentation for the agenda items below (in PDF format*) is available at: the Board of Supervisors' web site.
- Item #7
Contract No. 3564, "Bradshaw Interceptor Section 6A," Contract Change Order No. 2, An Increase Of $723,000.00, With Thirty-Five (35) Additional Calendar Days Added To Contract Time
- Item #8
Contract No. 80576, Approve Fifth Amendment To Agreement With Carollo Engineers To Provide Engineering Services For The 1998 Master Plan For The Sacramento Regional Wastewater Treatment Plant
- Item #9
Contract No. 80715, Approve Fourth Amendment To Agreement With MWH Americas, Inc., To Provide Engineering Services For The "Bradshaw Interceptor Section 6A"
- Item #10
Approve Agreement For Purchase Of Real Property In Connection With The Construction Of The "Arden Parallel Force Main Project"
- Item #11
DIRECTORS DISCUSSION OF ISSUES FOR FUTURE AGENDAS
- Item #12
Contract No. 52089, Authorize The District Engineer To Execute A Trunk Sewer Reimbursement Agreement With K. Hovnanian Forecast Homes, Inc., For The Design And Construction Of The "Natomas Central Trunk Sewer"
- Item #13
Contract No. 81087, Approve The Selection Of And Authorize The District Engineer To Execute An Agreement With Carollo Engineers To Provide Engineering Services For The Supervisory Control And Data Acquisition (SCADA) System Replacement